Date:January 23, 2017

Foz Tua dam (Portugal)

Development and implementation of Foz Tua Dam Emergency Plan (Portugal).

Foz tua 1 web

Lafcarr Project & Design and Energias de Portugal (EDP) sign a new contract. Tasks and duties to do will be related with the development and implementation of Foz Tua Dam Emergency Plan (Portugal).

Foz Tua 5 web

This project will be carried out in different phases from 2015 and 2017. It will consist of the following characteristics:

  • Installation of 14 electronic sirens in the dam coronation and affectation zones.
  • Creation of the Operation and Control Point (OCP) for isolated supervision and remote control of the devices: communication (VHF and GPRS radio) and
    software (remote control SCADA).
  • Information campaign with EDP of all the works done at the surrounding villages of Carrazeda de Ansiães, São João da Pesqueira, Alijó, Tabuaço, Sabrosa,
    Armamar, Peso da Régua and Lamego.Foz Tua 3 web