On 8 October 2025, between 10:00 and 14:00, sound tests (a drill) were carried out on the public warning system at the Foix dam, made up of five electronic sirens already in operation.
The project was built on the existing PEP (Dam Emergency Plan) and is integrated with iDAM, Lafcarr's own software, with remote control from the CECAT/ACA centre in Barcelona.
The work was carried out with Cardoner Group.
During the drill, readings were taken with calibrated sound level meters to check levels and coverage as part of the project validation plan.
The area covered mainly includes the municipality of Cubelles, among others downstream of the reservoir.
Video: emergency drill at the Foix dam (8 October 2025)
Drill on 8/10/2025 at the Foix dam: siren activation, audibility tests and coordination between Civil Protection, the Fire Service and ATLL with the integrated iDAM remote control system.